Calculator 06Power and capacity bottlenecks

Data Center Power Bottleneck Calculator

Convert announced facility MW into realistic active IT MW by testing the full power chain: credible grid supply, onsite generation, substations, cooling readiness, rack fit-out, silicon availability, and time-to-power. The output is what can actually turn into AI capacity.

Active facility MW

300 MW

60% of target facility load

Active IT MW

261 MW

39.1 MW facility overhead at 1.15 effective PUE

GPUs online

126K

83.7K GPU-equivalent gap

Binding bottleneck

Credible power supply

200 MW facility MW not yet usable

Online timing

56 mo.

Grid interconnection is the longest pre-handoff workstream

Effective power cost

$86.9/MWh

$14.9/MWh capacity adder

Constraint stack

Which layer limits usable AI capacity?

Credible power supply

Binding constraint

300 MW

Firm transformer capacity

Available capacity

450 MW

Cooling-ready capacity

Available capacity

345 MW

Rack fit-out capacity

Available capacity

322 MW

Available silicon capacity

Available capacity

382 MW

Target facility load

Available capacity

500 MW

Power bridge

Queued grid request500 MW
Credible queued MW300 MW
Already energized0.0 MW
Onsite generation0.0 MW
Firm transformers450 MW

Time to power

Partner delivery, grid work, and GPU turn-up

Grid interconnection

54 mo.

Critical path

HV transformers

18 mo.

Parallel workstream

Shell and MEP build

24 mo.

Parallel workstream

Cooling readiness

20 mo.

Parallel workstream

Schedule bridge

Data center hand-off

54 mo.

GPU install / test

2 mo.

Service slip

32 mo.

Workstreams run in parallel until the slowest one hands off the site. GPU installation then adds the turn-up and testing phase.

Delay cost

Monthly fixed carry$54.3M
Slip carrying cost$1.74B
Target online24 mo.

Power cost stack

Energy, capacity charges, facility carry, and capex

MetricValueUnitRead-through
Annual energy$174M$/yr2.42M MWh at 92% load factor
Annual capacity charge$36.0M$/yr$329/MW-day applied to active facility MW
Annual facility / colo cost$391M$/yr$125.00 / kW-mo on active IT load
Grid upgrade capex$200Mone-time$400.0K / queued MW
Total project capex$4.20Bone-time$8.0M / target facility MW plus grid upgrades
Power cost per GPU$1.7K$/GPU-yrEnergy plus capacity charges only

Sensitivity analysis

Grid credibility x onsite generation

Queue cred. \ onsite MW0.0 MW base0.0 MW base0.0 MW base50.0 MW100 MW
40%174 MW174 MW174 MW200 MW226 MW
50%217 MW217 MW217 MW239 MW261 MW
60% base261 MW261 MW261 MW278 MW280 MW
70%280 MW280 MW280 MW280 MW280 MW
80%280 MW280 MW280 MW280 MW280 MW

This grid holds transformers, cooling, rack fit-out, silicon, and schedule fixed while testing the most important siting question: how much of the queued grid request is real, and how much onsite power can bridge the gap?

Preset comparison

Same framework across grid, retrofit, BTM, and neocloud cases

PresetMarketTarget MWActive IT MWOnlineBottleneck
PJM greenfieldPJM500 MW261 MW56 mo.Credible power supply
ERCOT attestedERCOT500 MW285 MW32 mo.Credible power supply
Energized retrofitRemote US grid200 MW75.0 MW12 mo.Available silicon capacity
BTM overflowUS onsite generation300 MW183 MW17 mo.Available silicon capacity
CRWV rampMulti-region neocloud3.10 GW1.56 GW20 mo.Firm transformer capacity
GB200 liquidAI-ready hyperscale campus150 MW110 MW20 mo.Rack fit-out capacity